Unconventional BCGA

Valeura identified the potential for an unconventional Basin Centered Gas Accumulation (“BCGA”) play early in its entry into the Thrace Basin. Based on the BCGA thesis, the Company acquired the Banarli Exploration Licence in 2013 (adapted to two licences in 2015) and drilled the Kanzanci-5, Hayrabolu-10, and Yayli-1 wells to depths of 2,900 – 4,000 metres, into over-pressured sands, which provided more evidence supporting the BCGA play.

Under the Banarli Farm-In, the Company acquired approximately 500 square kilometres of 3D seismic (Karaca) and drilled the Yamalik-1 exploration well, fully funded by Equinor Turkey (“Equinor”), as the first well testing the BCGA thesis, into an area with no identified structural closure by design. The well encountered highly over-pressured gas saturated Mezardere and Kesan formations from approximately 2,900 metres down to the total depth of 4,196 metres. The over-pressure at the total depth was greater than 0.8 psi/ft based on testing results. The average net sand in the objective section was approximately 44 per cent.

In the fourth quarter of 2017, Valeura completed four production tests in the Kesan formation in the Yamalik-1 well, where each test was preceded by two slick-water high-pressure stimulations. The testing successfully demonstrated that gas and condensate would flow to surface post- high-pressure stimulation and a 24-hour aggregate production test rate of 2.9 MMcf/d was achieved. The gas flowed with a significant amount of condensate (with a test data range of 20 to 70 barrels per MMcf). The ability to flow high-pressure gas from an area outside of a structural closure supported the interpretation of an unconventional BCGA play.

Activities in 2018 focused on the planning and commencement of an appraisal program for the BCGA play, following the Yamalik-1 discovery, to determine whether the over-pressured gas is pervasive across the basin and to demonstrate that the gas could be flowed commercially. The notional program agreed with Equinor was to drill appraisal wells, including the second commitment well under the Banarli Farm-in, which would be high-pressure stimulated and tested if successful, and a notional plan to further production test one or two historic wells.

In September 2018, Valeura recompleted Yamalik-1 and tied-in the well to allow for loner-term production testing on a comingled basis. At the end of 24 hours of continuous production, the flow rate was 2.53 MMcf/d through a 20/64” choke with a wellhead pressure of 2,535 psi. After a period of intermittent flow of gas, condensate, and water, a gas lift compressor was installed to assist in the ongoing flow back of stimulation fluids phase of initial production. Pressures and flow rates stabilised after the introduction of gas lift, and the well continued to flow a mixture of gas, condensate and water. The Company is continuing to evaluate the well to better understand the flow potential of the different zones.

The first appraisal well, Inanli-1, funded by Equinor, was spudded in October 2018. The well was approximately 6 km from Yamalik-1 and the key objectives were to determine whether the over-pressured, gas-bearing reservoir discovered in Yamalik-1 is laterally continuous and is indicative of a BCGA, to test for effective reservoir and over-pressured gas at deeper depths than Yamalik-1, and to test for the presence of enhanced natural fracturing in the reservoir. Drilling operations carried into January 2019 when the well reached total depth at 4,885 metres. Based on drilling and wireline logging data, the well is interpreted to have intersected over-pressured tight gas below 3,270 metres down to the total depth. A programme to high-pressure stimulate the well and test select intervals began in Q2 2019.

The second appraisal well, Devepinar-1, funded 31.5 per cent by Valeura, is located 20 kilometres west of Yamalik-1 and Inanli-1 and was spudded in late February 2019. The well was drilled to 4,796 metres, and encountered clear indications of over-pressured gas throughout a 1,066 metre gross column in the Teslimkoy and Kesan Formations.  The well met all of its drilling objectives and most significantly, confirms the presence of over-pressured, gas-bearing reservoir at the western flank of the mapped BCGA fairway.  The well was cased and left in a state ready for testing and completion, which is planned to take place after Inanli-1’s testing and completion programme.

A significant portion of the Group’s value is in the natural gas prospective resource associated with the deep, unconventional basin-centered, gas/condensate play. This play is still in the early phase of exploration and appraisal and has both uncertainties and risk.

Whilst there are eight historic wells around the basin that are all interpreted to have encountered high-pressure gas at depth, the current well density in the basin and this play is still very low. There are uncertainties laterally across Valeura’s land interests, and vertically in the target Kesan Formation, as to the presence of gas, the pressure of any gas, and the amount of condensate in the gas. The ability to flow and recover gas commercially is still to be demonstrated. Most of the historic wells were drilled prior to high-pressure stimulation being a commonly accepted technique and none achieved a commercial flow rate using the perforation and testing techniques applied at the time in Turkey. Yamalik-1 was high-pressure stimulated and is still being tested.

In the near term, the Company’s focus is on better understanding the rocks’ flow characteristics through stimulation and testing.  Results from this programme will help define the forward programme for further appraisal activities.